George Douglass House Restoration Report for the quarter endinng June 30, 2021

George Douglass ยท July 2021

George Douglass House Restoration Project-Work Accomplished and In-Progress-2d Quarter 2021 Second quarter work in 2021 focused on plastering deteriorated areas, wall segments with partial or total de-lamination of original 1765 and/ or later applications, and patching voids. In the process of removing deteriorated or de-laminated plaster remnants in the or