Sites and Structures Report GDH, September 30, 2020
George Douglass House Work Progress, July 1-September 30, 2020 During this 3d quarter period, concentration was focused on parlor woodwork joinery and installation, as sequence details and Pandemic restrictions permitted. Our carpenters Tom & Chris Lainhoff continued the fabrication of parlor elements, built-in corner cabinetry, and molded millwork such a