Quarterly Status Report Form
Archives 1006.01.062

George Douglass House Restoration Report for the quarter endinng June 30, 2021

George Douglass · July 2021

George Douglass House Restoration Project-Work Accomplished and In-Progress-2d Quarter 2021 Second quarter work in 2021 focused on plastering deteriorated areas, wall segments with partial or total de-lamination of original 1765 and/ or later applications, and patching voids. In the process of removing deteriorated or de-laminated plaster remnants in the or

View record
2750
Photos 1005.01.133

Pipe-and-Plank scaffolding at south gable wall

Michael Fulp

Three-level scaffolding erected to provide work decking for reconstruction of the deteriorated stonework of the wall [see photo # 1158 in record MFR10PH6 for view of dismantled gable-end wall]; each deck was assembled after several “lifts” of stonework were laid up from the lower levels. This scaffolding system also includes a “flying-deck” level for rest