Joist extension

#1: Original floor boards in best parlor, leveled to hallway flooring
Archives 1008.01.081

Sites and Structures Report-GDH, June 30,2018

Sites and Structures Reports ยท June 30, 2018

George Douglass House Project Work April 1 to June, 30, 2018: During the 2d quarter of 2018, restoration carpenters Tom and Chris Lainhoff achieved significant progress toward restoring safe, stable, and historically and architecturally authentic flooring in the northwest ["best"] parlor of the house. A majority of the original floor boards have been preser