#1: Bundles of sawn plaster lath
Archives 1008.01.087

Sites and Structures Report GDH, December 31, 2019

Sites and Structures Reports · December 31, 2019

George Douglass House Restoration Project work accomplished October 1, 2019 to December 31, 2019: During this quarter substantial progress was achieved on first floor parlors, kitchen, and early store room in the categories of interior plasterwork, joinery, and painting with scientifically and precisely determined original colors: INTERIOR PLASTERWORK: For

View record
Image #1: chipped "keys" in base plaster; replaced lath and chair rail
Archives 1008.01.088

Sites and Structures Report GDH, June 30, 2020

Sites and Structures Reports · June 30, 2020

Work Progress during this 2d quarter period: interior plastering and woodwork joinery continued intermittently as weather, planning details, coordination between crafts, and Pandemic restrictions permitted. Our carpenters Tom & Chris Lainhoff continued to fabricate parlor elements such as wainscot paneling under windows [see Image #12], and best parlor wains

View record
#1: Preserved original [left] and new [right] plasterwork
Archives 1008.01.084

Sites and Structures Report-GDH, March 31, 2019

Sites and Structures Reports · March 31, 2019

George Douglass House Project work Accomplished January 1, 2019 to March 31, 2019 During the 1st quarter of 2019, our project plasterer (working on his 20th National Register structure) made substantial progress in the interior work, restoring wall integrity and surface finishes in the 2d floor chambers and hallway. This work progressed with the sensiti

View record