Sites and Structures Report GDH, December 31, 2019

Sites and Structures Reports · December 31, 2019

George Douglass House Restoration Project work accomplished October 1, 2019 to December 31, 2019: During this quarter substantial progress was achieved on first floor parlors, kitchen, and early store room in the categories of interior plasterwork, joinery, and painting with scientifically and precisely determined original colors: INTERIOR PLASTERWORK: For

View record
#1, photo 4: Reconstructed and plumbed west wall of Mouns Jones House
Archives 1008.01.074

Sites and Structures Report November 2016

Sites and Structures Reports · November 2016

I. MOUNS JONES HOUSE RESTORATION: During the late summer and early autumn of this year, the riverside wall of the Mouns Jones house was re-constructed from the foundation level to the timber plate [Image #1, photo 4, 10/10/16], which will bear the pocketed ends of the joists supporting the 2d story floor boards donated by the late Dr. Donald and Esther Shel

View record
#1 : Re-constructed corner cupboard in back parlor
Archives 1008.01.078

Sites and Structures Report-GDH, August 2020

Sites and Structures Reports · August 2020

Work Progress in George Douglass House, April 1-August 31, 2020: During this period, interior plastering and wood-work progressed in stages conforming to Pandemic restrictions as worker safety requires, including a rule allowing only one craftsman in the house on any work-day. The sequencing of plastering and woodwork was arranged to have all wooden "stops"

View record
#1: Restored woodwork in back parlor
Archives 1008.01.079

Sites and Structures Report-GDH, March 31, 2020

Sites and Structures Reports · March 2020

Work Progress in George Douglass House, Oct, 2019-March 30, 2020 During this six month period, interior plastering and woodwork joinery continued at a steady and coordinated pace as weather, planning details, and Pandemic restrictions permitted. Our carpenters Tom & Chris Lainhoff fabricated and installed major paneled elements, built-in corner cabinetry,